19.5.11

SAP Note 25879 - No check of cost element in general costs activities

Symptom:

If you create a general costs activity without cost element, the costs of this activity are not taken into account during costing.

Cause and prerequisites

It is not checked whether a cost element exists.

Solution
Check if a cost element exists, when you enter costs.