Despite the setting "any operation sequence for confirmations" in the confirmation parameters (transaction OPK4 field MRFLG), when you try to confirm a production order not in accordance with the operation sequence, error message RU024 is displayed.
Cause and prerequisitesThe milestone indicator is set for one of the control keys of the production order (can be set in Customizing OPJ8).
SolutionThe Customizing setting "any operation sequence" does not apply to milestone activities. If an operation is marked by the control key as a milestone, a preceding operation which is also declared as a milestone must at least be "partially confirmed".
Additional key words
Operation, sequence, confirmation, CO11, milestone