There are correctly configured process orders with phases and capacity requirements. You can find them in the capacity evaluation, but not in the planning table (neither in the tabular nor in the graphical one).
You are using the standard profile within the Capacity Leveling menu (transaction CMC0) and select the following function:
Capacity_Leveling->Resource_View->Plan._Table_(graph.) transaction CM29 or
Capacity_Leveling->Resource_View->Plan._Table_(table) transaction CM35
You are working in a customer client (e.g. <> client 000).
You have created a new client with client copy.
The reason is: You didn't copy the SAP standard customizing for capacity leveling into the new client. This is not done automatically by the client copy tool.
You can do that by calling transaction CMCE.
This step has to be executed for each new client.