Symptom:

If an already partially delivered sales order is rejected, the preliminary planning is not reduced during the goods issue of the respective delivery.
In addition, the MRP record for the sales order is retained with the planned quantity. The other requirement quantities are correct (=0).

Cause and prerequisites

Program error. The preliminary planning must be activated.

Solution
Please make the following corrections in program FV50VF0A: