If you append a long text to an activity of a WBS element and press F3, a popup is displayed whether you want to schedule although no changes relevant to scheduling were made.
Cause and prerequisitesIncorrect source code
Solutionsee below
Additional key words
Project planning board, time scheduling, project time scheduling, planning according to structure
CJ21, CJ23, CJ20, CJ27, CJ2A, CJ2B, CJ2C, CJ2D, activity text