SAP Note 27232 - Finite schedul.: Occupancy gap after capa. change

Symptom:

Planning board: An operation is dispatched for a capacity. You change the available capacity interactively. Then you reschedule the operation. The original BOM item of this operation can now no longer be used by other operations. There is always a gap in occupancy.

Cause and prerequisites
Solution
Source code corrections

Additional key words

Finite scheduling