You can define cycle lengths or offset lengths that are not the multiple of one day (for example, cycle length = 36 hours) or that are less than one day. This causes incorrect results during the scheduling because the scheduling is only carried out on a daily basis.
Cause and prerequisitesThe query whether the cycle length or offset length is an exact multiple of one day was not programmed so far.
SolutionI. 3.0 System: Please implement correction P30K015379.
II. 2.2/2.1 Systems: Please implement correction P22K009678.
If you are using a 2.1 System, please replace correction P22K009678 by P21K005932.