In Capacity leveling or Capacity evaluation no load is appearing.
See Advice note 15274. Some customizing from SAP needs to be copied into your working client.
Other reasons are due to customizing.
- 1. Control key does not have capacity swithced on.
- 2. Your operation does not have any work.
- 3. You need to have a duration aswell if you wish to see the operation on the graphical planning table.
- 4. The workcenter does not have a valid formular in the capacity header. The "OTHER" formular should have SAP008 (Standard entry).
- 5. The scheduling is also not going to work properly if you do not have a formular in the scheduling screen. (Standard SAP004).
- 6. As an extra tip costs should be calculated using SAP008. See assignments.
- 7. If you have defined your capacity category to be machine rather than labour, then you will not see these objects on the Planning table when start the planning table from PM or SM menus. You will only see them when you start the planning table from PP See Tran. CM00 for all options.