Symptom:

When creating new WBS elements (without copying) the following values are not included from the project definition:
PROJ-VERNR Number of the person responsible (project manager)
PROJ-VERNA Person responsible (project manager)
PROJ-ASTNR Number of the applicant
PROJ-ASTNA Applicant
PROJ-JIBCL JIB/JIBE Class
PROJ-JIBSA JIB/JIBE Sub-class

Cause and prerequisites

Program error

Solution
Correction
If you are making this correction and you have Release 2.1, then you should not include the lines containing the following fields:
JIBCL JIB/JIBE Class
JIBSA JIB/JIBE Sub-class
These fields are not a part of Release 2.1.

Additional key words

Transactions
CJ01 Create work breakdown structure
CJ02 Change work breakdown structure
CJ11 Create WBS element
CJ12 Change WBS element