In program "SAPLCYBT", exception "PROGRAM_ERROR" was triggered by a RAISE statement. The termination occurred in ABAP/4 program "SAPLCYBT" in "CY_BT_KBED_OPR_UPDATE".
Cause and prerequisitesThe 'Calculate capacity requirements' indicator is cancelled in an order or a network which was scheduled with capacity requirements calculation. Then an operation or sub-operation or activity element is created and the 'Calculate capacity requirements' indicator is set again or a function, for example, Release Order, is performed which resets the indicator. The above-mentioned error occurs if a scheduling is carried out then.
SolutionFirst set the 'Calculate capacity requirements' indicator and then carry out the scheduling. Include the operation or sub-operation or activity element and carry out the scheduling again.
Program correction
Additional key words
Scheduling