The scheduling log reports message C7008 "Date is not defined in factory calendar" although the scheduling dates are within the defined factory calendar.
Cause and prerequisitesIntervals of available capacity are maintained in a work center capacity whose 'To date' is after the expiration date of the factory calendar. The error does not occur if the date is 12/31/9999.
SolutionThe 'To date' of an interval of available capacity must be maintained so that it is within the validity period of the factory calendar. The exception is the date 12/31/9999, which is allowed.
Additional key words
CR02
Scheduling, capacity leveling