SAP Note 26141 - Schdlng log: Date not defined in factory calendar

Symptom:

The scheduling log reports message C7008 "Date is not defined in factory calendar" although the scheduling dates are within the defined factory calendar.

Cause and prerequisites

Intervals of available capacity are maintained in a work center capacity whose 'To date' is after the expiration date of the factory calendar. The error does not occur if the date is 12/31/9999.

Solution
The 'To date' of an interval of available capacity must be maintained so that it is within the validity period of the factory calendar. The exception is the date 12/31/9999, which is allowed.

Additional key words

CR02
Scheduling, capacity leveling