Message CR134 "No authorization to reflect the change in the HR System." when attempting to create or maintain a Work Center
Cause and prerequisitesThis message arises because the user is not authorised to maintain information in the HR-PD (Personnel Planning and Development) module.
Occurs only if the interface between Logistics and HR is enabled, via Customizing.
In HR, if WorkCenters are changed, a corresponding Work Center is changed in Logistics.
In Logistics, if Work Centers are changed, a corresponding change is made to the HR work center.
To make this change, the user needs HR authorisation.
Resolution:
If INTEGRATION between Logistics and HR is not required, CHANGE configuration.
< 3.0
Path:Configuration>Logistics>PM>PM Planning>Work center>HR Interface Ensure that the HR Active flag is not selected.
In 3.0, via the IMG,
PM -> Preventative Maintance -> Work Centers -> Activate Interface to Human Resources.
Else,
Give the user the following authorisation object..
Object PLOG,
Infotype 1000,
Planning status 1
Object Type A,
Plan Version to match that specified in the configuration,
Function Code INSE, AEND, DISP etc
Subtype
Additional key words
IR01 IR02 SAPMC68A CR134