26.2.11

SAP Note 23753 - Copy plan versions without orders for the project

Symptom:

In Project system, when you perform the functions
"Copy plan version--> costs" (CJ9B) and
"Copy plan version--> revenues" (CJ9C)
only the values planned directly on the WBS elements are copied.
The planning values of orders or networks for the project are not taken into account when copying.

Cause and prerequisites

Function not supported in R/3-3.0.

Solution
This function is planned for a later release.
If only CO orders are allocated to the project, the corresponding copy function in the CO orders application can be used in R/3-3.0.

No comments:

Post a Comment