Goods movements (and reservations) of a material can be proposed and entered with decimal places even when the quantity has a unit of measure that is restricted to whole numbers (for example, a piece).
This applies, for example, to goods withdrawals for a reservation or for a production order, or backflushing for a goods movement for provision of material for a subcontractor order, when the quantity is not counted in whole pieces.
MB01, T006
Works as designed. This procedure ensures that, for partial withdrawals, the percentage of the costs is correctly charged.
Example:
If 1 PC of a material is used to produce 10 KG of a material, then an inwards goods movement of 1 kg of the produced materials will cause 0.1 PC of the material to be charged.
If you want to post the goods movements in whole numbers only, correct the proposed withdrawal quantities when you enter the goods movement.