When you enter a completion confirmation, the system issues the message CK060 'Valuation not carried out for the costing object' in the costing log. When the confirmation is saved, the order is not debited with actual costs.
Cause and prerequisitesInsufficient data maintained
SolutionPlease check that,
- a work center is defined for the confirmation / operation
- the costing indicator is set in the control key of the confirmed operation
- the external processing indicator is set in the control key of the confirmed operation
- a cost center with activity types has been defined for the work center specified in the confirmation, and that the activity types are valid on the posting date of the confirmation (Transaction: CR03, Goto -> Assignments -> Cost center assign.)
- activity types are also assigned to the operation in the routing (these have been copied from the work center and may have been changed)
- activity values are entered for the activity types maintained in the operation in the routing
- activity prices have been defined for the specified activity dates and are valid on the posting date (Transaction KP23)