Program: SAPMM61X
Error ID: 123
The materials planning in transaction MD01, MD02 or MD03 terminates with error message 61123 'Error determining planning periods calendar &'.
This may be due to several reasons:
- 1. The planning calendar is insufficiently maintained. There are MRP items (requirements, planned orders, production orders, purchase orders, and so on, ... ) with a requirements date or an input date before or after the period that is defined in the planning calendar.
- 2. Program error in Releases 3.0F and 3.1G. The program error only occurs if you are working with planned finish = period end in the lot-sizing procedure.
- 1. Check the requirements dates and delivery dates of the MRP items of the material in question with the current stock/requirements list in transaction MD04. Enhance the calendar with transaction MD26 'Change Planning Calendar' so that these dates will be considered.
Additional key words
E61123
Key word: Planning period
No comments: